The U.S. Department of Energy and the North Carolina Clean Energy Technology Center are excited to announce that a new, modernized DSIRE is under construction. The new version of DSIRE will offer significant improvements over the current version, including expanded data accessibility and an array of new tools for site users. The new DSIRE site will be available in December 2014. Staff are currently working hard on the new version of DSIRE but are also maintaining the content of the current version of DSIRE. Thank you for your continued support and patience during this transition. We hope you are as excited for December as we are!

US Department Energy Efficiency and Renewable Energy
IREC North Carolina Solar Center
Home Glossary Links FAQs Contact About Twitter    Facebook
West Virginia

West Virginia

Incentives/Policies for Energy Efficiency

Printable Version
Interconnection Standards   

Last DSIRE Review: 08/18/2014
Program Overview:
State: West Virginia
Incentive Type: Interconnection
Eligible Efficiency Technologies: CHP/Cogeneration
Eligible Renewable/Other Technologies: Solar Thermal Electric, Photovoltaics, Landfill Gas, Wind, Biomass, Hydroelectric, Geothermal Electric, Fuel Cells, Small Hydroelectric, Renewable Fuels, Fuel Cells using Renewable Fuels
Applicable Sectors: Commercial, Industrial, Residential, Agricultural
Applicable Utilities:All utilities
System Capacity Limit:2 MW
Standard Agreement:Yes
Insurance Requirements:Vary by system size and/or type; levels established by PSC
External Disconnect Switch:Not required for inverter-based systems up to 25 kW; utility's discretion for all other systems
Net Metering Required:No
Authority 1:
Date Enacted:
W. Va. PSC Order, Case No. 06-0708-E-GI
12/12/2006
Authority 2:
Date Enacted:
Date Effective:
W. Va. Code ยง 24-2F-1 et seq.
06/02/2009
07/01/2009
Authority 3:
Date Enacted:
Date Effective:
West Virginia PSC 150-33-1
06/30/2010
08/30/2010
Authority 4:
Date Enacted:
Date Effective:
West Virginia General Order 258.1
05/19/2011
07/18/2011
Summary:
In 2006, West Virginia stakeholders came together to consider net metering, interconnection as required by the Federal Energy Policy Act (2005) and agreed upon a "Statement of Consensus Among Parties," which was presented to and accepted by the West Virginia Public Service Commission (PSC) in December 2006. The consensus agreement did include interconnection guidelines for the state, however, the PSC did not initiate a formal rule-making or incorporate the guidelines into agency rules. Rather, the interconnection guidelines were incorporated into utility net metering tariffs (which are proposed by the utilities). In 2010, the PSC opened a docket to reconsider net metering and interconnection per H.B. 103 (2009). The Order, General Order No. 258, adopted new interconnection standards (Rules Governing Electric Utility Net Metering Arrangements and Interconnections), based almost entirely on the existing interconnection guidelines of the consensus agreement. However, several important improvements were incorporated, including tiered insurance requirements and removing the requirement for external disconnect switches in the case of smaller, inverter-based systems.

West Virginia's interconnection standards include two levels of review. The qualifications and application fees for each level are as follows:
  • Level 1 applies to certified, inverter-based systems with a rated capacity of 25 kilowatts (kW) or less. The maximum application fee for Level 1 applicants is $30.
  • Level 2 applies to certified systems with a capacity of 2 MW or less that do not meet the criteria for inclusion in Level 1. The maximum application fee is $50 plus $1 per kW of capacity.
General Order 258.1 was issued in September 2011 to correct an omission related to the Level 2 Interconnection Agreement. In May 2011, the Commission corrected the omission by incorporating provisions relating to assignment, liability, indemnity, Force Majeure, consequential damages, and default into the standard Level 2 Interconnection Agreement. These rules are effective July 18, 2011.

The rules use IEEE 1547 as the technical standard of evaluation. The rules specify the technical screens which may be applied to applications at each level of review as well as time limits for different stages of the evaluation process. Application forms and interconnection agreements are standardized.

Customer-generators must maintain $100,000 general liability for systems with nameplate capacity of 50 kW or less, $500,000 for systems with nameplate capacity of greater than 50 kW to 500 kW, and $1 million for systems with name plate capacity greater than 500 kW. Utilities may not require customers to install an external disconnect switch for inverter-based, certified systems 25 kW or less.

 
Contact:
  General Information - PSC
West Virginia Public Service Commission
201 Brooks Street
P.O. Box 812
Charleston, WV 25323
Phone: (800) 344-5113
Fax: (304) 340-0325
NCSU - home
Disclaimer: The information presented on the DSIRE web site provides an unofficial overview of financial incentives and other policies. It does not constitute professional tax advice or other professional financial guidance, and it should not be used as the only source of information when making purchasing decisions, investment decisions or tax decisions, or when executing other binding agreements. Please refer to the individual contact provided below each summary to verify that a specific financial incentive or other policy applies to your project.

While the DSIRE staff strives to provide the best information possible, the DSIRE staff, the N.C. Solar Center, N.C. State University and the Interstate Renewable Energy Council, Inc. make no representations or warranties, either express or implied, concerning the accuracy, completeness, reliability or suitability of the information. The DSIRE staff, the N.C. Solar Center, N.C. State University and the Interstate Renewable Energy Council, Inc. disclaim all liability of any kind arising out of your use or misuse of the information contained or referenced on DSIRE Web pages.

Copyright 2013 - 2014 North Carolina State University, under NREL Subcontract No. XEU-0-99515-01. Permission granted only for personal or educational use, or for use by or on behalf of the U.S. government. North Carolina State University prohibits the unauthorized display, reproduction, sale, and/or distribution of all or portions of the content of the Database of State Incentives for Renewables and Efficiency (DSIRE) without prior, written consent.