| State: |
Rhode Island |
| Incentive Type: |
Interconnection |
| Eligible Renewable/Other Technologies: |
Solar Thermal Electric, Photovoltaics, Wind, Biomass, Hydroelectric, Geothermal Electric, Anaerobic Digestion, Small Hydroelectric, Ocean Thermal, Fuel Cells using Renewable Fuels |
| Applicable Sectors: |
Commercial, Industrial, Residential, Nonprofit, Schools, Local Government, State Government, Fed. Government, Multi-Family Residential, Agricultural, Institutional |
| Applicable Utilities: | Investor-owned utilities |
| System Capacity Limit: | Not specified |
| Standard Agreement: | No |
| Insurance Requirements: | Not addressed |
| External Disconnect Switch: | Not addressed |
| Net Metering Required: | No |
Authority 1:
Date Enacted:
Date Effective:
|
R.I. Gen. Laws ยง 39-26.3
6/29/2011
6/29/2011
|
Rhode Island enacted legislation (HB 6222) in June 2011 to standardize the application process for the interconnection of customer-sited renewable-energy systems to the state’s distribution grid. Rhode Island’s interconnection policy is not nearly as comprehensive as interconnection standards established by many other states. The new application process, which took effect in July 2011, applies to the state's electric distribution companies, including National Grid.
Under this process, an interconnection applicant must submit an application to the utility for an impact study, including a request for an estimate of the cost of interconnecting the proposed system. The applicant may choose to request a feasibility study prior to requesting an impact study. The utility must provide a feasibility study, if requested, within 30 days of receipt of a completed application, and it must provide an impact study within 90 days of receipt of a completed application.
There is no feasibility study fee for residential systems up to 25 kilowatts (kW) that comply with UL 1741.1. There is a $50 fee for residential systems greater than 25 kW that comply with UL 1741.1. For non-residential systems, the feasibility study fee ranges from $100 to $2,500, depending on system size and whether the system complies with UL 1741.1.
There is no impact study fee for residential systems up to 25 kW that comply with UL 1741.1. There is a $100 fee for residential systems greater than 25 kW that comply with UL 1741.1. For non-residential systems, the impact study fee ranges from $500 to $10,000, depending on system size and whether the system complies with UL 1741.1. This fee structure will remain in effect through December 31, 2012. The Rhode Island Public Utilities Commission (PUC) is authorized to raise fee levels beginning January 1, 2013.
National Grid has incorporated these provisions into its "Standards for Interconnection of Distributed Generation." These standards are included in National Grid's tariffs, which are accessible via the PUC's web site.