Last DSIRE Review: 10/15/2012
Program Overview:
| State: |
Puerto Rico |
| Incentive Type: |
Net Metering |
| Eligible Renewable/Other Technologies: |
Photovoltaics, Wind, "Other Sources" of Renewable Energy, Other Distributed Generation Technologies |
| Applicable Sectors: |
Commercial, Industrial, Residential, Nonprofit, Schools, Local Government, State Government, Multi-Family Residential, Agricultural, Institutional |
| Applicable Utilities: | PREPA
|
| System Capacity Limit: | 5 MW for non-residential connected to transmission or sub-transmission lines per Act 103 of 2012; 1 MW for non-residential connected to distribution lines; 25 kW for residential
|
| Aggregate Capacity Limit: | No limit specified
|
| Net Excess Generation: | Credited to customer's next bill at retail rate (with certain limitations); excess reconciled annually
|
| REC Ownership: | Not addressed
|
| Meter Aggregation: | Not addressed
|
| Web Site: |
http://www.aeepr.com/medicionneta/
|
Authority 1:
Date Enacted:
Date Effective:
|
2007 PR LS 114
08/16/2007
08/16/2007
|
Authority 2:
Date Enacted:
Date Effective:
|
S2377 (2008) Act No. 211
08/09/2008
08/09/2008
|
Authority 3:
Date Enacted:
Date Effective:
|
PREPA Reglamento 7579 (Net Metering Regulations - In Spanish)
09/2008
10/07/2008
|
Authority 4:
|
Unofficial Translation of Puerto Rico Net Metering Rules
|
Authority 5:
Date Enacted:
Date Effective:
|
S.B. 2472 (Act 103)
06/05/2012
06/05/2012
|
Summary:
Puerto Rico enacted net-metering legislation in August 2007, allowing customers of Puerto Rico Electric Power Authority (PREPA) to use electricity generated by solar, wind or "other" renewable-energy resources to offset their electricity usage. This law applies to residential systems with a generating capacity of up to 25 kilowatts (kW) and non-residential systems up to one megawatt (MW) in capacity.*
Customer net excess generation (NEG) is carried over as a kilowatt-hour (kWh) credit to the following month, but NEG credit is limited to a "daily maximum" of 300 kWh for residential customers and 10 megawatt-hours (MWh) for commercial customers. Customers with excess credits remaining at the end of a 12-month period (ending in June) will be compensated as follows: 75% of the excess credits will be purchased by PREPA at a rate of $0.10 per kWh or "the amount resulting from the subtraction of the adjusted fuel fee based on the variable costs incurred by the public corporation exclusively for the purchase of fuel and energy, from the total price charged by the public utility to its customers, converted into kilowatt-hours, whichever is greater;" and the remaining 25% will be granted to PREPA to distribute as a credit or reduction applied to the electricity bills of public schools.
System owners must, at their own expense, use a bi-directional meter installed by an expert electrician. Systems must comply with the standards and specifications on minimum efficiency requirements established by the Puerto Rico Energy Affairs Administration (EAA) or another designated government body. In 2008, legislation (S2377 Ley 211) was enacted that removed the requirement that systems be installed by a North American Board of Certified Energy Practitioners (NABCEP) installer, and instead established that all systems must be installed by an electrical engineer or expert electrician that is registered with the EAA and meets the additional EAA requirements for renewable energy system installers. Yet, legislation enacted in 2012 applies this NABCEP requirement again. All equipment must be guaranteed for at least five years by the manufacturer or distributor. Installations must incorporate emissions and noise-control mitigation measures, when applicable.
PREPA adopted the necessary regulations for compliance with this law in October 2008 and established the procedures for applying for net metering. A net metering application (in Spanish) is available on PREPA's website. PREPA and EAA must also develop and implement educational campaigns designed to inform consumers of the benefits of net metering and of available renewable-energy technologies.
* Senate Bill 2472 increased the capacity limit to 5 MW for non-residential customers connected to transmission or sub-transmission lines. The regulations have not yet been updated to reflect the changes implemented by the new law.
|
Contact:
| |
PREPA Customer Service
Autoridad de EnergĂa Electrica de Puerto Rico
Puerto Rico Electric Power Authority
PO Box 364267
San Juan, PR 00936-4267
Phone: (787) 289-3434
Fax: (787) 289-4120
E-Mail: servicios@prepa.com
Web Site: http://www.prepa.com
|
| |
| |
General Info EAA
Energy Affairs Administration
P.O. Box 41314
San Juan, PR 00940
Phone: (787) 332-0914
Fax: (787) 721-3089
Web Site: http://www.aaepr.net/
|
|
|