Oregon Incentives/Policies for Renewables & Efficiency |
 |
Last DSIRE Review: 03/06/2013
Program Overview:
| State: |
Oregon |
| Incentive Type: |
Energy Standards for Public Buildings |
| Eligible Efficiency Technologies: |
Comprehensive Measures/Whole Building, Specific technologies not identified |
| Applicable Sectors: |
State Government |
| Requirement: | New state construction must exceed the energy conservation provisions of the Oregon State Building Code by 20% or more |
| Web Site: |
http://www.oregon.gov/ENERGY/CONS/SEED
|
Authority 1:
|
ORS 276.900 et seq.
|
Authority 2:
|
OAR 330-130-0010 et seq.
|
Summary:
Oregon's State Energy Efficiency Design Program (SEED) was originally established in 1991. This program, codified in state law, directs state agencies to work with the Oregon Department of Energy to ensure cost-effective energy conservation measures (ECMs) are included in new construction projects and major renovations to public buildings. Leased buildings are also required to be more energy efficient.
The law was revised in 2001 to require that all state facilities constructed on or after June 30, 2001, exceed the energy conservation provisions of the Oregon State Building Code by at least 20%. Existing buildings must reduce energy use by 20% compared to the building's baseline energy use in 2000. Energy conservation and efficiency projects in existing buildings can be funded through energy savings performance contracts. Complete SEED guidelines are available on the web site listed above.
|
|
 |
Disclaimer: The information presented on the DSIRE web site provides an unofficial overview of financial incentives and other policies. It does not constitute professional tax advice or other professional financial guidance, and it should not be used as the only source of information when making purchasing decisions, investment decisions or tax decisions, or when executing other binding agreements. Please refer to the individual contact provided below each summary to verify that a specific financial incentive or other policy applies to your project.
While the DSIRE staff strives to provide the best information possible, the DSIRE staff, the N.C. Solar Center, N.C. State University and the Interstate Renewable Energy Council, Inc. make no representations or warranties, either express or implied, concerning the accuracy, completeness, reliability or suitability of the information. The DSIRE staff, the N.C. Solar Center, N.C. State University and the Interstate Renewable Energy Council, Inc. disclaim all liability of any kind arising out of your use or misuse of the information contained or referenced on DSIRE Web pages.
|