Nebraska Incentives/Policies for Renewables & Efficiency |
 |
Last DSIRE Review: 07/06/2012
Program Overview:
| State: |
Nebraska |
| Incentive Type: |
Interconnection |
| Eligible Renewable/Other Technologies: |
Photovoltaics, Landfill Gas, Wind, Biomass, Geothermal Electric, Anaerobic Digestion, Small Hydroelectric |
| Applicable Sectors: |
Commercial, Industrial, Residential, Agricultural |
| Applicable Utilities: | All utilities |
| System Capacity Limit: | 25 kW |
| Standard Agreement: | No |
| Insurance Requirements: | "Additional" liability insurance not required for systems that meet certain technical standards
|
| External Disconnect Switch: | Not addressed |
| Net Metering Required: | Yes |
Authority 1:
Date Enacted:
Date Effective:
|
R.R.S. 70-2001, et seq.
5/13/2009
5/13/2009
|
Summary:
Nebraska enacted legislation in May 2009 (LB 436), establishing general rules for interconnecting and net metering systems that generate electricity. Nebraska's policy applies to systems that use solar, wind, methane, biomass, hydropower or geothermal resources to produce electricity and have a rated capacity of 25 kilowatts (kW) or less.
To be eligible, a facility must meet all applicable safety, performance, interconnection and reliability standards established by the National Electric Code and adopted by the State Electrical Board, the National Electric Safety Code, and the Institute of Electrical and Electronics Engineers. The system must also be capable of automatically isolating itself from the electrical grid in the event of a power outage, but a utility-accessible external disconnect switch is not required.
Customers must request an inspection of their system from the State Electrical Division and provide documentation of the completed inspection to their utility before the system may be interconnected to the distribution grid. The utility must provide a bi-directional meter to the customer at no additional cost to the customer. The utility may not require a customer-generator to purchase additional liability insurance if all safety and interconnection requirements are met.
|
|
 |
Disclaimer: The information presented on the DSIRE web site provides an unofficial overview of financial incentives and other policies. It does not constitute professional tax advice or other professional financial guidance, and it should not be used as the only source of information when making purchasing decisions, investment decisions or tax decisions, or when executing other binding agreements. Please refer to the individual contact provided below each summary to verify that a specific financial incentive or other policy applies to your project.
While the DSIRE staff strives to provide the best information possible, the DSIRE staff, the N.C. Solar Center, N.C. State University and the Interstate Renewable Energy Council, Inc. make no representations or warranties, either express or implied, concerning the accuracy, completeness, reliability or suitability of the information. The DSIRE staff, the N.C. Solar Center, N.C. State University and the Interstate Renewable Energy Council, Inc. disclaim all liability of any kind arising out of your use or misuse of the information contained or referenced on DSIRE Web pages.
|