The U.S. Department of Energy and the North Carolina Clean Energy Technology Center are excited to announce that a new, modernized DSIRE is under construction. The new version of DSIRE will offer significant improvements over the current version, including expanded data accessibility and an array of new tools for site users. The new DSIRE site will be available in December 2014. Staff are currently working hard on the new version of DSIRE but are also maintaining the content of the current version of DSIRE. Thank you for your continued support and patience during this transition. We hope you are as excited for December as we are!

US Department Energy Efficiency and Renewable Energy
IREC North Carolina Solar Center
Home Glossary Links FAQs Contact About Twitter    Facebook
North Carolina

North Carolina

Incentives/Policies for Renewables & Efficiency

Printable Version
Hyde County - Wind Energy Facility Ordinance   

Last DSIRE Review: 05/08/2012
Program Overview:
State: North Carolina
Incentive Type: Solar/Wind Permitting Standards
Eligible Renewable/Other Technologies: Wind
Applicable Sectors: Commercial, Industrial, Residential, Nonprofit, Schools, Local Government, Utility, State Government, Tribal Government, Multi-Family Residential, Agricultural, Institutional
Authority 1:
Date Enacted:
Date Effective:
Hyde County Code of Ordinances Sec. 16-43, et seq.
11/3/2008
11/4/2008
Summary:

Hyde County, located in eastern North Carolina, adopted a wind ordinance in 2008 to regulate the use of wind energy facilities throughout the county, including waters within the boundaries of Hyde County. The ordinance is substantially similar to the model wind ordinance drafted by the North Carolina Wind Working Group, and establishes parameters for the permitting process, minimum setbacks, noise and shadow flicker, installation and design, and decommissioning of retired systems.

For the purposes of this ordinance, wind energy facilities are classified as "small" if they consist of a single wind turbine with a rated generating capacity of 20 kilowatts (kW) or less, "medium" if one or more wind energy facilities have a total rated capacity of more than 20 kW but not greater than 100 kW, "large" if they have a total rated capacity of more than 100 kW.

Permitting Process: All new wind energy facilities, or expansions of existing facilities must receive a permit from the County Manager prior to construction. A permit application must include a narrative describing the facility; approximate generating capacity; the proposed number and height of all wind turbines to be built; location of the proposed site; a detailed site plan; certification of compliance with local, state and federal regulations; an environmental assessment for large wind facilities; decommissioning plans; financial assurance that the owner can pay for decommissioning; and documentation of an agreement between the system owner and adjacent landowners.

Setbacks: The setback is calculated by multiplying the required setback number by the wind turbine height and measured from the center of the wind turbine base to the property line, building or road. Setbacks are generally determined by the following table:

Wind Energy Facility Type Occupied Buildings on Participating Landowner Property Occupied Buildings on Non-Participating Landowner Property Property Lines on Non-Participating Landowner Property Public Roads
Small System 0.0 1.5 1.1 1.5
Medium System 1.1 2.0 1.5 1.5
Large Scale 1.1 2.5 1.5 1.5




Setbacks may be waived under certain conditions when all affected parties agree to different terms.

Noise and Shadow Flicker: Noise and shadow flicker issues for small and medium wind energy facilities are addressed by setbacks, or will be addressed by existing noise ordinances. Audible sound from a large or utility scale wind energy facility should not exceed fifty-five dBA, as measured at any occupied building of a non-participating landowner. Shadow flicker at any occupied building on an adjacent property caused by a large or utility scale wind energy facility located within 2,500 ft of the building shall not exceed thirty hours per year. These restrictions may be waived under certain conditions.

Installation and Design: The installation of wind energy facilities must conform to all applicable industrial standards, including those of the American National Standards Institute, and shall conform to floodplain and wind zone requirements. Towers and rotor blades must be of a non-obtrusive color such as white, off-white or gray. Wind energy facilities must also remain free from advertising, including flags, streamers and other decorative items, as well as artificial lighting, except that which is required by the Federal Aviation Administration (FAA). Any on-site transmission or power lines must, to the extent possible, be placed underground.

Fees: Permit applications are subject to a non-refundable fee to be established periodically by resolution of the Board of Commissioners.


 
Contact:
  Public Information
Hyde County
Planning and Economic Development
30 Oyster Creek Road
PO Box 188
Swan Quarter, NC 27885
Phone: (252) 926-4180
E-Mail: hydecopl@yahoo.com
Web Site: http://www.hydecountync.gov/departments/planning.php
NCSU - home
Disclaimer: The information presented on the DSIRE web site provides an unofficial overview of financial incentives and other policies. It does not constitute professional tax advice or other professional financial guidance, and it should not be used as the only source of information when making purchasing decisions, investment decisions or tax decisions, or when executing other binding agreements. Please refer to the individual contact provided below each summary to verify that a specific financial incentive or other policy applies to your project.

While the DSIRE staff strives to provide the best information possible, the DSIRE staff, the N.C. Solar Center, N.C. State University and the Interstate Renewable Energy Council, Inc. make no representations or warranties, either express or implied, concerning the accuracy, completeness, reliability or suitability of the information. The DSIRE staff, the N.C. Solar Center, N.C. State University and the Interstate Renewable Energy Council, Inc. disclaim all liability of any kind arising out of your use or misuse of the information contained or referenced on DSIRE Web pages.

Copyright 2013 - 2014 North Carolina State University, under NREL Subcontract No. XEU-0-99515-01. Permission granted only for personal or educational use, or for use by or on behalf of the U.S. government. North Carolina State University prohibits the unauthorized display, reproduction, sale, and/or distribution of all or portions of the content of the Database of State Incentives for Renewables and Efficiency (DSIRE) without prior, written consent.