Georgia Incentives/Policies for Renewables & Efficiency |
 |
Last DSIRE Review: 04/17/2013
Program Overview:
| State: |
Georgia |
| Incentive Type: |
Interconnection |
| Eligible Renewable/Other Technologies: |
Photovoltaics, Wind, Fuel Cells, Fuel Cells using Renewable Fuels |
| Applicable Sectors: |
Commercial, Industrial, Residential, Nonprofit, Schools, Local Government, State Government, Fed. Government, Institutional |
| Applicable Utilities: | All utilities
|
| System Capacity Limit: | 100 kW for non-residential; 10 kW for residential
|
| Standard Agreement: | No |
| Insurance Requirements: | "Additional" liability insurance not required for systems that meet certain technical standards
|
| External Disconnect Switch: | Not addressed |
| Net Metering Required: | Yes |
Authority 1:
Date Enacted:
Date Effective:
|
O.C.G. ยง 46-3-50 et seq.
4/28/2001
6/1/2002
|
Summary:
The Georgia Cogeneration and Distributed Generation Act of 2001 allows residential electricity customers with photovoltaic (PV) systems, wind-energy systems or fuel cells up to 10 kilowatts (kW) in capacity, and commercial facilities up to 100 kW, to connect to the grid. The aggregate capacity of distributed generation systems is limited to 0.2% of a utility's system peak demand from the previous year.
Interconnected customers must comply with all relevant national standards, including those established by the Institute of Electrical and Electronic Engineers (IEEE), Underwriters Laboratories (UL), and the National Electrical Safety Code (NEC). Furthermore, the Georgia Public Service Commission (PSC) may adopt additional safety, power-quality and interconnection requirements. There is no provision in Georgia's interconnection standards requiring customers to install a manual external disconnect device. Utilities may not require additional tests or additional liability insurance.
|
|
 |
Disclaimer: The information presented on the DSIRE web site provides an unofficial overview of financial incentives and other policies. It does not constitute professional tax advice or other professional financial guidance, and it should not be used as the only source of information when making purchasing decisions, investment decisions or tax decisions, or when executing other binding agreements. Please refer to the individual contact provided below each summary to verify that a specific financial incentive or other policy applies to your project.
While the DSIRE staff strives to provide the best information possible, the DSIRE staff, the N.C. Solar Center, N.C. State University and the Interstate Renewable Energy Council, Inc. make no representations or warranties, either express or implied, concerning the accuracy, completeness, reliability or suitability of the information. The DSIRE staff, the N.C. Solar Center, N.C. State University and the Interstate Renewable Energy Council, Inc. disclaim all liability of any kind arising out of your use or misuse of the information contained or referenced on DSIRE Web pages.
|